Remodeling

January '04
Architect's plans

01/21/04 - 02/14/04 (26 pictures)
Underpinning, slab removal, digging down

02/18/04 - 02/19/04 (14 pictures)
Scenes of devastation - New sewer line and water line

02/25/04 (5 pictures)
Subsoil Drain & waterproofing

03/09/04 (12 pictures)
Waste drains & preparation for steel I-Beam

03/12/04 (7 pictures)
Steel I-Beam installed

03/18/04 (5 pictures)
Preparation for pouring the new slab

03/23/04 (3 pictures)
The new slab & start of framing

04/06/04 (5 pictures)
Rough framing

04/25/04 (7 pictures)
New windows, window well, subfloor, ductwork

05/16/04 (9 pictures)
Rough Plumbing

06/29/04 (10 pictures)
Strucutured wiring

08/05/04 (6 pictures)
Drywall. Finally.

10/17/04 (6 pictures)
Drywall taped sanded & primed. Doors installed.

10/22/04 (3 pictures)
Heatmat installed, tiling begun

10/24/04 (3 pictures)
Bathroom tiling continued

10/27/04 (4 pictures)
Bathroom tiling continued

10/31/04 (5 pictures)
Bathroom tiling continued

11/03/04 (5 pictures)
Hardwood floor

11/14/04 (7 pictures)
Finish Plumbing

11/15/04 (5 pictures)
Shower Finish Plumbing

12/22/04 (8 pictures)
Finished floor, screen

There is also a thread about our project on the AVSForum here.